The estimated cost of the Trans Mountain pipeline expansion project has increased once again, this time to $30.9 billion.
That’s the latest figure from Trans Mountain Corp., the federal Crown corporation that owns the pipeline. On Friday, Trans Mountain Corp.
blamed the latest cost overruns on a number of factors, including inflation, labour and supply chain challenges, flooding in B.C. and unexpected major archeological discoveries along the route.
The new price tag is a 44 per cent increase from the $21.4 billion cost projection placed on the pipeline expansion project a year ago, and more than double an earlier estimate of $12.6 billion.
Previous cost increases were blamed on the COVID-19 pandemic, scheduling pressures related to permitting processes, and route changes to avoid culturally and environmentally sensitive areas, among other things.