Swedish construction faces “crisis situation” as environmental court shuts down cement factory

Construction in Sweden could grind to a halt after the country’s biggest cement factory was stripped of its licence to mine limestone on environmental grounds.

The ruling by the Swedish Supreme Land and Environmental Court last week means that the Cementa plant at Slite in Gotland could be forced to end production on 1 November.

Matilda Hoffstedt, manager of the plant, said the ruling would create “a crisis situation for Swedish cement supply” while Cementa said work on Foster + Partners’ Slussen masterplan in Stockholm could be impacted.

However, Greenpeace campaign manager Carl Schlyter welcomed the decision.

“It is wonderful that the court chooses to comply with the environmental laws we have, not to aggravate the species crisis and that incomplete environmental impact assessments are not accepted,” Schlyter told Swedish news organisation Dagens PS.

Sweden’s second-largest CO2 emitter

The plant produces around three-quarters of all the cement used in Sweden. It is also the second-largest source of greenhouse gas emissions in the country, responsible for three per cent of all CO2 emissions.

The court ruling overturns an earlier decision by a lower court to grant the factory a licence to continue mining limestone, an essential ingredient in cement, for another 20 years.

“They tossed out their application to keep on mining limestone,” said Daniel Jacobs, a journalist working at Dagens PS. “Now the construction industry is saying they’re not going to be able to build anything in Sweden.”

The licence was refused due to concerns over the impact on groundwater in the environmental assessment the factory had submitted. Greenpeace has also accused the plant of using its kilns to incinerate toxic waste without a permit.

Keep reading on Dezeen.com


Check out more news below:

  • Build Innovation 2024 - Box ad
  • Keith Walking Floor - Box - Sept 2021
  • Premier - Box
  • Chicago Build 2024 - Box
  • Metcalcon 2024
  • CWRE 2024
  • UAV Expo 2024 - Box
  • Dentec - Skeet Safe - Box
  • RAIC Vancouver Conference 2024
  • IAPMO R&T
  • Procore Box 2024
  • Groundbreak 2024 - Box