PCL Tallest Freestanding Crane
May 26, 2026

Reaching New Heights: How PCL Erected the Tallest Freestanding Crane in Company History

At the QEII Halifax Infirmary Expansion Project, a record-setting crane is helping PCL overcome complex challenges, reduce risk, and provide schedule certainty for the owner on one of the country’s largest healthcare projects.


Beneath the shadow of the landmark Halifax Citadel, work is underway on the largest health care infrastructure project in Atlantic Canada’s history.

The Halifax Infirmary Expansion Project (HIEP) includes a 14-story tower that will house operating rooms, an intensive care unit and an emergency department twice the size of the current facility.

Given the project’s height and its large footprint, it became clear early in planning that multiple cranes would be required to efficiently move construction materials round the massive site.

Complex Challenges, Innovative Solutions

When it comes to construction tower cranes, there are several options, but they generally fall under two categories: freestanding and tied-in or braced cranes.

For multifloor, high-rise construction, tied-in cranes are more common because they can reach greater heights. They use the structures themselves for support, and their heights are increased or “climbed” as new floors are added to the project. However, the climbing process takes time and incurs extra costs. Those expenses and associated schedule risks were key considerations for the publicly funded project where predictability and continuity of work were critical.

Keep reading this article on PCL.com


Explore related articles you won’t want to miss:

Quarter Century Platinum Status for PCL Construction

Building the Backbone of AI: How Data Center Construction is Powering the Future of Digital Life

  • 6th Annual Modular Prefab & Construction-Tech - Box
  • London Build 2026 - Box