Inaccurate time tracking costs up to 8% of payroll — but the real damage is corrupted job cost data. Here’s what contractors actually lose.
It’s Wednesday afternoon. A job is two weeks in — eight-person crew, industrial coating contract, $340,000 scope.
The PM calls the office and asks how they’re tracking on labor.
The office pulls the job cost report. “$87,400 labor to date. You’re within budget.”
The PM makes a decision: no schedule adjustment, no crew change, no flag to the client.
The job closes four weeks later. Final payroll reconciliation runs. True labor: $112,800.
The difference? Hours logged to the wrong cost codes. Supervisors filling in timesheets from memory. A few employees who clocked out of the job but kept working. Nothing dramatic. Just the ordinary, daily noise of inaccurate time tracking — accumulated over six weeks into a $25,400 swing that nobody saw coming because the data in the system was wrong the whole time.
The cost of inaccurate time tracking in construction goes well beyond payroll errors. The direct payroll hit is real — up to 8% of total payroll in paper-based operations. But the damage that actually kills jobs is what bad time data does to your job costing. Wrong hours corrupt cost records. Corrupt cost records produce decisions that accelerate losses. And by the time the right number appears, the window to act is already closed.