Command Center Blog: Rogers-O’Brien Construction Slashes Project Time and Costs Using COMMAND Center

Rogers-O’Brien implemented COMMAND Center on a 16-story, 300,000 square foot mixed-use project. By using COMMAND Center to determine when concrete achieved necessary strength and to reduce test cylinders, the team saved one day of construction schedule per floor, for a total savings of … Continue reading Command Center Blog: Rogers-O’Brien Construction Slashes Project Time and Costs Using COMMAND Center