Changing the skyline in Kitimat

The skyline at our site in Kitimat is changing! Last week we lifted and placed the main absorber column. At 54m in length and weighing over 800 tonnes, it is the largest piece of equipment at our site. The successful lift was executed using 3 cranes over several hours.

This milestone comes just two weeks after we placed the precoolers and main cryogenic heat exchanger.

Watch to hear about the planning and teamwork involved to execute this lift safely.

Courtesy of LNG Canada