Thursday, September 26, 2024
  • Premier Construction Software - Leaderboard New - Sept 5
  • Revizto - Leaderboard - September and October 2024
  • Dentec - Leaderboard - 2023 - Updated
  • Sage Leaderboard
  • CWRE 2024
  • Canadian Concrete Expo 2025 - Leaderboard
  • Procore Leaderboard 2024
  • NIBS - Digital Twins 2024
  • IAPMO R&T Lab - Leaderboard
  • Keith Walking Floor - Leaderboard - Sept 2021
Soo Lock project (1)
June 15, 2023

New Soo Lock project sticking to the schedule

The U.S. Army Corps of Engineers’ New Lock at the Soo project remains on schedule as major construction continues with phases 2 and 3 this season.

Joint ventures Kokosing-Alberici (Upstream Approach Walls, Phase 2), and Kokosing, Alberici, Traylor (New Lock, Phase 3) have a busy construction season ahead of them.

“Since resuming major construction this season, the Phase 2 contractor has placed 13 concrete caps, bringing the total caps placed to 68 and preparation for placement of new steel sheets, steel posts and concrete panel wall are in progress,” New Lock Senior Project Manager Mollie Mahoney said. “The Phase 3 contractor plans to focus on demolition of aging structures, extensive electrical work, bridge construction, and coffer dam construction to allow for dewatering.” 

Phase 3 excavation work will include blasting activities, which will be communicated with stakeholders as blasting activities get closer.

“Beginning May 30, the Hydro Plant tailrace closed to recreational boaters. The normal schedule for the tailrace is: closed Mondays at 6 a.m.

through Saturdays at 6 p.m. and open Saturdays at 6 p.m. through Mondays at 6 a.m.” New Lock Chief Mick Awbrey said. “The closure is necessary to ensure the safety of all boaters and marine construction workers as large barges, cranes and construction boats will be working in the area.”

Phase 1 included deepening the upstream approach to the New Lock from 24 feet to 30 feet deep so modern vessels can approach the New Lock at the Soo and concluded in August 2022, under budget and ahead of schedule.

Phase 2 includes rehabilitating the upstream approach walls to stabilize the existing approach walls allowing modern vessels to tie up and wait their turn to pass through the New Lock at the Soo. The estimated completion date for Phase 2 is summer 2024.

Keep reading on sootoday.com


  • CWRE 2024
  • Dentec - Leaderboard - 2023 - Updated
  • IAPMO R&T Lab - Leaderboard
  • Premier Construction Software - Leaderboard New - Sept 5
  • NIBS - Digital Twins 2024
  • Keith Walking Floor - Leaderboard - Sept 2021
  • Canadian Concrete Expo 2025 - Leaderboard
  • Revizto - Leaderboard - September and October 2024
  • Procore Leaderboard 2024
  • Sage Leaderboard